"DEPLOYMENT OF RESOURCES AND CLOSE MONITORING ENSURES TIMELY COMPLETION"

Construction Week

|

February 2023

MD Dr. Nalin Gupta - J. Kumar Infraprojects Ltd, has always maintained that the interests of clients must be met, especially in the complex projects they execute

"DEPLOYMENT OF RESOURCES AND CLOSE MONITORING ENSURES TIMELY COMPLETION"

You have done some commendable work across the metro projects in Mumbai. Can you tell us about the extensive work done?

 We at J. Kumar are proud that we have contributed to the construction of Metro rail in Mumbai. Recently Metro Line 2A and Line 7 were dedicated by Honourable Prime Minister Shri Narendra Modi Ji to Mumbaikars. J. Kumar has undertaken the EPC construction of Line 2A and line 7 comprising of 35km of viaduct and 30 stations constructed in 2 phases. Phase I with 20km of viaduct and 18 stations which were open to the public in April 2022. Phase II of Line 2A and Line 7 comprises 15km viaduct and 12 stations. We have also undertaken finishing and facade works of major stations.

We are confident about our ability to undertake complex project, its timely completion, and delivering quality work to the satisfaction of the client. We completed DN Nagar Metro station of Line 2A (Mumbai Metro) in record time with 285 numbers of precast elements which were launched for three-tier DN Nagar station in just 100 days, which itself is a record.

What were some of the advanced technologies and machineries deployed for these projects?

For the first time in India, we have used straddle carrier of capacity 155 ton for the erection of Pier cap, l-girders, U-girders and other precast station elements in Line 09 (Mumbai Metro).

Construction Week'den DAHA FAZLA HİKAYE

Construction Week

Construction Week

LOOK DOWN; GET FLOORED

The flooring industry is thriving as new developments, redevelopments and renovations across sectors continue to happen

time to read

6 mins

September 2025

Construction Week

Construction Week

A BLUEPRINT FOR GROWTH

Aakash Ohri, Joint Managing Director and Chief Business Officer at DLF Home Developers, discusses expansion, luxury housing demand, and strategic focus.

time to read

6 mins

September 2025

Construction Week

Construction Week

SMOOTH OPERATIONS

Road repair equipment are in full swing use across the country. We know why

time to read

6 mins

September 2025

Construction Week

Construction Week

MAHA GOVT PLANS ₹6.6K CR SHIPYARD CLUSTER

A consultant being appointed to conduct a techno-economic feasibility study.

time to read

1 min

September 2025

Construction Week

Construction Week

MOVING THE WORLD

Material handling equipment have become more rampant across sites as larger projects need materials movement

time to read

6 mins

September 2025

Construction Week

Construction Week

YOGI ANNOUNCES ₹30K CR PLAN FOR BRAJ

UP govt orders housing devt authorities to expedite land aggregation for greenfield townships.

time to read

1 mins

September 2025

Construction Week

Construction Week

WHITE LOTUS UNVEILS ₹700 CR INVESTMENT PLAN

Times expansion with a structural shift in India's luxury housing market.

time to read

1 mins

September 2025

Construction Week

Construction Week

FADNAVIS QUESTIONS RISING REAL ESTATE PRICES

Hands over keys to homeowners of BDD redevelopment project in Worli, Mumbai.

time to read

1 mins

September 2025

Construction Week

Construction Week

SHOULDERING INDIA'S INFRASTRUCTURE AMBITIONS

Versatile backhoe loader machines are reshaping India's infrastructure, driven by tech innovation, policy, and rising demand.

time to read

4 mins

September 2025

Construction Week

Construction Week

INDIA SURPASSES UK, USA IN HPI

India's residential property market posts 7.7% annual price growth in Q1-2025, outperforming the United States, United Kingdom, and Australia.

time to read

1 min

September 2025

Translate

Share

-
+

Change font size