"DEPLOYMENT OF RESOURCES AND CLOSE MONITORING ENSURES TIMELY COMPLETION"

February 2023

|

Construction Week

MD Dr. Nalin Gupta - J. Kumar Infraprojects Ltd, has always maintained that the interests of clients must be met, especially in the complex projects they execute

"DEPLOYMENT OF RESOURCES AND CLOSE MONITORING ENSURES TIMELY COMPLETION"

You have done some commendable work across the metro projects in Mumbai. Can you tell us about the extensive work done?

 We at J. Kumar are proud that we have contributed to the construction of Metro rail in Mumbai. Recently Metro Line 2A and Line 7 were dedicated by Honourable Prime Minister Shri Narendra Modi Ji to Mumbaikars. J. Kumar has undertaken the EPC construction of Line 2A and line 7 comprising of 35km of viaduct and 30 stations constructed in 2 phases. Phase I with 20km of viaduct and 18 stations which were open to the public in April 2022. Phase II of Line 2A and Line 7 comprises 15km viaduct and 12 stations. We have also undertaken finishing and facade works of major stations.

We are confident about our ability to undertake complex project, its timely completion, and delivering quality work to the satisfaction of the client. We completed DN Nagar Metro station of Line 2A (Mumbai Metro) in record time with 285 numbers of precast elements which were launched for three-tier DN Nagar station in just 100 days, which itself is a record.

What were some of the advanced technologies and machineries deployed for these projects?

For the first time in India, we have used straddle carrier of capacity 155 ton for the erection of Pier cap, l-girders, U-girders and other precast station elements in Line 09 (Mumbai Metro).

المزيد من القصص من Construction Week

Construction Week

Construction Week

STEELING THE SHOW

Steel structures are becoming increasingly central to the construction industry value chain. Know how steel is strengthening India's building future.

time to read

10 mins

December 2025

Construction Week

Construction Week

ALUK INDIA TARGETS 100 ALUK HOME CENTRES AND ₹250 CR SYSTEMS REVENUE BY FY2027-28

The company charts bold India growth strategy as it celebrates a major milestone and outlines its 2027-28 ambitions.

time to read

5 mins

December 2025

Construction Week

Construction Week

FASTER GREENER GROWTH

A silent revolution is underway as RMC and automated batching plants reshape how Indian developers build faster and cleaner.

time to read

10 mins

December 2025

Construction Week

Construction Week

FY26 HOME SALES TO GROW 20% IN VALUE

While sales volume dropped 14% y-o-y in FY 2025, sales value jumped 6%, reports Anarock.

time to read

1 min

December 2025

Construction Week

Construction Week

BUILDING ON GROWTH MOMENTUM

Mahindra Lifespace Developers MD and CEO, Amit Kumar Sinha examines real estate trends spanning redevelopment, policy direction, and demand shifts.

time to read

9 mins

December 2025

Construction Week

Construction Week

EXCON 2025: THE BIG REVEAL

EXCON 2025 is set to showcase India's shift to smarter, sustainable, digitally driven construction equipment designed for faster and greener infrastructure growth.

time to read

7 mins

December 2025

Construction Week

Construction Week

GCCS TO CREATE 40 LAKH JOBS BY 2030: STUDY

A report by TeamLease shows India's GCC sector currently employs 19 lakh people.

time to read

1 min

December 2025

Construction Week

Construction Week

What makes rebar coupler testing seismically relevant

Comprehensive testing and recognised certifications ensure that rebar couplers can withstand earthquake stresses without compromising structural integrity.

time to read

2 mins

December 2025

Construction Week

Construction Week

BRIDGES AND FLYOVERS: INDIA'S NEW CONNECTIVITY PUSH

\"We anticipate widespread adoption of automation, AI-based design optimisation, electric equipment usage in urban zones, and smart sensors embedded in structures for real-time condition monitoring.\"

time to read

10 mins

December 2025

Construction Week

Construction Week

MAIA ESTATES SECURES RS 120 CR FUNDING

Maia Estates has secured Rs 120 crore in funding from Arnya, a real estate investment firm, to develop The Seven, a residential project in Basavanagudi, South Bengaluru. Construction is expected to start in early 2026 and completion by 2029.

time to read

1 min

December 2025

Translate

Share

-
+

Change font size