"DEPLOYMENT OF RESOURCES AND CLOSE MONITORING ENSURES TIMELY COMPLETION"
Construction Week
|February 2023
MD Dr. Nalin Gupta - J. Kumar Infraprojects Ltd, has always maintained that the interests of clients must be met, especially in the complex projects they execute
-
You have done some commendable work across the metro projects in Mumbai. Can you tell us about the extensive work done?
We at J. Kumar are proud that we have contributed to the construction of Metro rail in Mumbai. Recently Metro Line 2A and Line 7 were dedicated by Honourable Prime Minister Shri Narendra Modi Ji to Mumbaikars. J. Kumar has undertaken the EPC construction of Line 2A and line 7 comprising of 35km of viaduct and 30 stations constructed in 2 phases. Phase I with 20km of viaduct and 18 stations which were open to the public in April 2022. Phase II of Line 2A and Line 7 comprises 15km viaduct and 12 stations. We have also undertaken finishing and facade works of major stations.
We are confident about our ability to undertake complex project, its timely completion, and delivering quality work to the satisfaction of the client. We completed DN Nagar Metro station of Line 2A (Mumbai Metro) in record time with 285 numbers of precast elements which were launched for three-tier DN Nagar station in just 100 days, which itself is a record.
What were some of the advanced technologies and machineries deployed for these projects?
For the first time in India, we have used straddle carrier of capacity 155 ton for the erection of Pier cap, l-girders, U-girders and other precast station elements in Line 09 (Mumbai Metro).
यह कहानी Construction Week के February 2023 संस्करण से ली गई है।
हजारों चुनिंदा प्रीमियम कहानियों और 10,000 से अधिक पत्रिकाओं और समाचार पत्रों तक पहुंचने के लिए मैगज़्टर गोल्ड की सदस्यता लें।
क्या आप पहले से ही ग्राहक हैं? साइन इन करें
Construction Week से और कहानियाँ
Construction Week
REHLKO ENERGY INDIA
ALOK KUMAR, ASSOCIATE DIRECTOR - SALES AND SERVICE
1 min
January 2026
Construction Week
L&T CONSTRUCTION AND MINING MACHINERY BUSINESS (L&T CMB)
ARVIND K GARG, ADVISOR TO L&T CHAIRMAN AND MANAGING DIRECTOR
1 min
January 2026
Construction Week
WIRTGEN INDIA
FRANK BETZELT, SR VP, WIRTGEN INTERNATIONAL DR VOLKER KNICKEL, CEO, WIRTGEN GROUP RAMESH PALAGIRI, MD AND CEO, WIRTGEN INDIA
2 mins
January 2026
Construction Week
TATA MOTORS
RAJESH KAUL, VICE PRESIDENT AND BUSINESS HEAD - TRUCKS
1 min
January 2026
Construction Week
KOBELCO CONSTRUCTION EQUIPMENT INDIA
MOSES EDDY, DIRECTOR, DIVISION HEAD - SALES AND AFTER SALES
1 min
January 2026
Construction Week
NORD DRIVESYSTEMS
AMIT DEVKULE, SALES DIRECTOR
1 min
January 2026
Construction Week
AFCONS WINS MOST INNOVATIVE COMPANY AWARD 2025
Receives the national-level honours at CII Industrial Innovation Awards 2025 across sectors and service categories.
1 min
January 2026
Construction Week
DAMAC UNVEILS TROPICAL DREAM WITH ISLANDS 2
Dubai-based private developer eyes ten-fold increase in master-planned communities over next 10 years
2 mins
January 2026
Construction Week
PUTZMEISTER CONCRETE MACHINES
Putzmeister Concrete Machines plans to drive adoption of intelligent batching plants in India, betting on productivity, safety and technology-led operations as infrastructure activity picks up from 2026, Debjeet Chatterjee, General Manager – Strategy and Business Development, Putzmeister Concrete Machines India told Construction Week at EXCON 2025.
1 min
January 2026
Construction Week
GMMCO LTD
CHANDRASHEKAR V, MD AND CEO
1 min
January 2026
Translate
Change font size