Power Delayed, Promise Intact
Energy & Power
|EP_23_03 (Energy & Power Vol 23 Issue 03 July 16, 2025)
The Rooppur Nuclear Power Plant, Bangladesh's most ambitious infrastructure project, is still facing delays, slowed by sanctions on Russia, blocked payments, and equipment delivery setbacks. Hopes now rest on fuel loading beginning in December 2025, if the IAEA gives its approval. Despite lacking global oversight, the project has managed to avoid cost overruns. But without clear communication and strong leadership, progress has stalled. Even so, many still believe Rooppur can help power a more secure and self-reliant energy future for Bangladesh.
The long-anticipated start of operations at the Rooppur Nuclear Power Plant (RNPP), Bangladesh's most ambitious and costly infrastructure project to date, may be pushed back once again. Still, hopes are high that fuel loading for the first 1,200 MW unit could begin by December this year, pending a final round of inspections and sign-off by a team of global and local experts. Even if that milestone is reached, it will take at least another 12 months before the unit is provisionally handed over and commercial operations can begin. Full synchronization and production at designed capacity might not happen until the end 2026. In the meantime, preparations for completion of construction and installation of equipment and accessories in the second unit are expected to move forward.
Across the globe, 35 countries have already entered the nuclear power club. Bangladesh and Turkey are now in a quiet race to become the 36th. Turkey, using the same VVER-1200 reactor technology, is building a 2,400 MW plant and also has its sights set on beginning test runs this December.
According to officials at the contractor and the Nuclear Power Generation Company Bangladesh Limited (NPGCBL), while groundwork for Rooppur began back in 2011, actual construction didn't get underway until 2017. The second unit followed about nine months later. Now, the first 1,200 MW unit is in its final stretch, with testing and inspection activities in full swing. Construction on the second unit is also moving ahead steadily.
Industry insiders emphasize that the project has remained under strict international oversight from day one, in keeping with global protocols for the peaceful use of nuclear technology. Both the International Atomic Energy Agency (IAEA) and Bangladesh's own Atomic Energy Regulatory Authority are supervising progress. As part of this tightly controlled process, the IAEA must grant final clearance before any fuel can be loaded into the reactor.
このストーリーは、Energy & Power の EP_23_03 (Energy & Power Vol 23 Issue 03 July 16, 2025) 版からのものです。
Magzter GOLD を購読すると、厳選された何千ものプレミアム記事や、10,000 以上の雑誌や新聞にアクセスできます。
すでに購読者ですか? サインイン
Energy & Power からのその他のストーリー
Energy & Power
Govt Agencies Must Lead Transition to Renewable Energy: Rizwana
Environment, Forest and Climate Change Adviser Syeda Rizwana Hasan has said that all government agencies must transition to renewable energy within the next two to three years to set an example for the nation.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
Carbon Markets Key to Bangladesh's Green Growth: Experts
Experts highlighted the potential of carbon markets to boost climate investments and promote sustainable growth in Bangladesh.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
Vietnam, Singapore Step Up Cooperation on Energy, Trade, Technology
Vietnamese Minister of Industry and Trade Nguyễn Hồng Dikn and Singaporean Minister-in-Charge of Energy, and Science and Technology in the Ministry of Trade and Industry Tan See Leng have agreed to continue close coordination in implementing key areas of cooperation, particularly in energy, industry, trade, and science and technology.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
Tk 1,200cr Lost in Missed Savings as Pipeline Sits Idle
Bangladesh has lost around Tk 1,200 crore in missed savings over the last one and a half years due to the delay in commercial launch of a dual pipeline that can carry imported oil directly from Cox's Bazar's Maheshkhali to Patenga in the port city.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
BD Seeks Korean Investments in Textiles, Electronics, Renewables
The Bangladesh Investment Development Authority (BIDA) has urged Korean investors to leverage Bangladesh's dynamic investment landscape, highlighting the country's strategic advantages and ongoing pro-business reforms aimed at facilitating foreign (FDI).
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
India Issues 3.6 GW of New RE Tenders
India has issued 3,600 megawatts (MW) of renewable energy tenders in September under the project development category.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
Shipping Corporation Wants to Operate Pipeline
State-owned Bangladesh Shipping Corporation sent a proposal to the energy ministry through the shipping ministry on June 19, expressing its interest in operating the pipeline with assistance from a third party.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
Climate Tipping Points Being Crossed, Scientists Warn
Global warming is crossing dangerous thresholds sooner than expected, with the world’s coral reefs now in an almost irreversible die-off, marking what scientists recently described as the first “tipping point” in climate-driven ecosystem collapse.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
Energy Adviser Blames Section of Politicians, Businessmen for Crisis in Gas Sector
Adviser of the Ministry of Power, Energy and Mineral Resources Muhammad Fouzul Kabir Khan recently said a section of politicians and their allied businessmen have created the ongoing crisis in the gas sector.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Energy & Power
Frequent Power Outages Leave Sunamganj Residents in Despair
Daily life in 12 upazilas of Sunamganj has been thrown into disarray as residents endure up to 18 hours of load-shedding each day due to an acute power shortage.
1 min
EP_23_10 (Energy & Power Vol 23 Issue 10- COP30 Special - November 1, 2025)
Listen
Translate
Change font size