THE COAST IS CLEAR
Construction Week|August 2021
An update on the entire Mumbai Coastal Road Project
THE COAST IS CLEAR

While the world is seeing an unprecedented crisis with the pandemic, Mumbai, a very important island, and one of the most important cities in India is seeing a project that was only hitherto imagined. And who else, but none other than Municipal Corporation of Greater Mumbai (MCGM) is executing it.

On 8 June 2015, the coastal road project received its first clearance from the Union Ministry of Environment and Forests but received the final clearance on 11 May 2017. There is a long history to the coastal road and one that dates back to 1962, according to information available in the public domain.

Today, the 29.80 km Mumbai Coastal Road Project (MCRP) is an under-construction access-controlled expressway with a route connecting Princess Street Flyover in South Bombay with Kandivali in the northern suburbs. In early July, the Brihanmumbai Municipal Corporation (BMC) declared that it has completed 36% of the total work of the coastal road project, against the 40% target it had set for completion by mid- 2021. But the pandemic had a large role in delaying most of the plans around the globe.

Total length:29.80 km

Cost of project:

Rs 12,721 crore

It also said that 90% of the fill, 68% of the sea wall, and 11% of the double tunnel have been completed. The work of coastal road is going on day and night uninterruptedly!” the BMC said in a statement.

The completed work includes about 470 meters (m) or 25% of tunneling work of one tunnel and reclamation of 105 hectares (ha) of the total 111ha. At present, the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress.

Esta historia es de la edición August 2021 de Construction Week.

Comience su prueba gratuita de Magzter GOLD de 7 días para acceder a miles de historias premium seleccionadas y a más de 8500 revistas y periódicos.

Esta historia es de la edición August 2021 de Construction Week.

Comience su prueba gratuita de Magzter GOLD de 7 días para acceder a miles de historias premium seleccionadas y a más de 8500 revistas y periódicos.

MÁS HISTORIAS DE CONSTRUCTION WEEKVer todo
PROOF IS IN THE ROOF
Construction Week

PROOF IS IN THE ROOF

Roofing, cladding and waterproofing are not concerns that you constantly need to spend on, if you get it first time right

time-read
6 minutos  |
June 2024
SAVE YOURSELF
Construction Week

SAVE YOURSELF

Green buildings are the way to go if you want to live a healthier life and also save the environment

time-read
7 minutos  |
June 2024
THE LONG VIEW
Construction Week

THE LONG VIEW

Facades, fenestration and cladding are now more high-end and sophisticated. What has evolved?

time-read
5 minutos  |
June 2024
PRUDENT PURSUITS
Construction Week

PRUDENT PURSUITS

Ajay Ashar, CMD, Ashar Group, is known for his meticulous approach and commitment towards his projects that help him stand out among peers in the competitive real estate market

time-read
5 minutos  |
June 2024
MACE TO TRANSFORM AHMEDABAD RAILWAY STATION
Construction Week

MACE TO TRANSFORM AHMEDABAD RAILWAY STATION

The redevelopment project covers almost 40 hectares

time-read
1 min  |
June 2024
RITES INKS PACT WITH BANGLADESH RAILWAY
Construction Week

RITES INKS PACT WITH BANGLADESH RAILWAY

Rites has been a old partner in Bangladesh's path to infrastructure development

time-read
1 min  |
June 2024
K RAHEJA CORP HOMES' MAIDEN VENTURE IN SION
Construction Week

K RAHEJA CORP HOMES' MAIDEN VENTURE IN SION

Will feature 3, 3.5, and 4-bed homes with decks

time-read
2 minutos  |
June 2024
GODREJ JARDINIA HITS RS 2,000 CRORE BOOKING VALUE!
Construction Week

GODREJ JARDINIA HITS RS 2,000 CRORE BOOKING VALUE!

Sector 146 is a prominent upcoming residential corridor in Noida

time-read
1 min  |
June 2024
TRIFECTA PROJECTS UNVEILS TRIFECTA VANTO
Construction Week

TRIFECTA PROJECTS UNVEILS TRIFECTA VANTO

Is located in the prime area of Sarjapur Road

time-read
2 minutos  |
June 2024
KANODIA GROUP TARGETS RS 1000 CR REVENUE
Construction Week

KANODIA GROUP TARGETS RS 1000 CR REVENUE

The location of the acquired land is considered prime

time-read
1 min  |
May 2024