Next year, global engineering and technology company Sener will continue to provide the engineering, procurement and construction services for the 100 MW Kathu concentrated solar power (CSP) project in South Africa’s Northern Cape, in conjunction with its joint venture partner Acciona.
Construction commenced in May and is due for completion at the end of 2018. The work includes installations of electrical and mechanical components for all of the reflective mirrors and the central power processing plant.
Sener regional MD Siyabonga Mbanjwa says most of the key components of the solar field, such as pylons, solar collector elements, torque tubes and arms, will be manufactured, galvanised, supplied and erected in 2017, with most of the manufacturing taking place in South Africa.
The solar field for this project is approximately 375 ha in size and has a total of 12 500 piles, over 500 000 m 3 of cut and 600 000 m 3 of fill of earthworks. Sener provides the technology for the solar field, which consists of parabolic mirrors that reflect sunrays and concentrates them into a receiver – a specific tube with good heat absorptivity properties – through which a fluid passes, he explains.
Mbanjwa outlines that the power plant’s system works by the heat-transfer fluid transmitting the generated heat either into the molten salts thermal storage system or directly into the steam power generation system. This enables the molten salts thermal storage system to store enough energy to maintain the turbine for five hours while working at full load.
Bu hikaye Engineering News dergisinin December 16, 2016 baskısından alınmıştır.
Binlerce özenle seçilmiş premium hikayeye ve 9.000'den fazla dergi ve gazeteye erişmek için Magzter GOLD'a abone olun.
Zaten abone misiniz? Oturum aç
Engineering News'den DAHA FAZLA HİKAYE
Engineering News
Seeking Advice
Govt appoints consultants to help decide future course for airlines
4 mins
Engineering News 2 December 2016
Engineering News
Project to add 260 000 jobs by 2019
With its objective of increasing the economic contribution of three key focus sectors by up to R59-billion, the Western Cape government has put in place its Project Khulisa growth strategy, which also aims to add about 260 000 jobs across these sectors.
3 mins
Engineering News 2 December 2016
Engineering News
Energy Efficiency & Management
Importance of energy efficiency highlighted at DoE conference.
4 mins
December 09, 2016
Engineering News
Biofuels
Innovation earns company biofuels award.
4 mins
December 09, 2016
Engineering News
Security Technology For Business
Power instability leads to security technology changes in South Africa.
3 mins
December 09, 2016
Engineering News
Corridor Crowd­-In
eThekwini seeks private investment around public­transport corridor.
3 mins
December 16, 2016
Engineering News
Taking Off
Fourteen airport rail links planned in Africa, including two more in SA.
8 mins
December 16, 2016
Engineering News
New gas projects will be economical – Aurecon
With two major gas-to-power projects under way in the country, consulting company Aurecon believes that the two, possibly three, gas power stations associated with the projects can be economical as existing infrastructure can be used to support them.
3 mins
December 16, 2016
Engineering News
Construction to continue at Kathu
Next year, global engineering and technology company Sener will continue to provide the engineering, procurement and construction services for the 100 MW Kathu concentrated solar power (CSP) project in South Africa’s Northern Cape, in conjunction with its joint venture partner Acciona.
3 mins
December 16, 2016
engineering news
pipes, tubes & hoses
appeals for pipeline upgrades unheeded.
2 mins
january 20, 2017
Translate
Change font size