The first tunnel section of the Elizabeth Line – better known as Crossrail – is due to open next December between Paddington and Abbey Wood via Canary Wharf. Keith Fender has been given an exclusive tour of Farringdon, one of the major interchange points on the £16billion project
On December 9 the tunnel section of the Elizabeth Line under central London will open to passengers, with services between Paddington and Abbey Wood via Canary Wharf running 15 times an hour in each direction. As this issue closed for press, there were 28 days before dynamic testing will begin, fewer than 300 days before the first public trains begin operation.
The first thing anyone entering the work site opposite Smithfield Market sees is a digital countdown to live testing of Class 345 trains through the station. Everyone who works there, and visitors, can’t help but notice this as it’s deliberately placed to be noticed. Visiting the station site on November 24, 2017 there were 92 and a half days left before this was planned to start on February 24. Arriving on the almost finished platforms, it was apparent the station had yet to receive overhead electrification; the section from Farringdon to Liverpool St was due to receive the aluminium overhead conductor rail during January.
Building Farringdon’s Crossrail station - seven years of construction
Construction work began in the Farringdon area in 2011 when the BAM Ferrovial Kier (BFK) consortium of civil engineering contractors responsible for the site started the first preparatory underground piling – this was done before the tunnel boring machines (TBMs) digging the tunnels under London were anywhere near Farringdon.
In 2012, three shafts to the future running tunnel level were dug and from these, parts of the new station site were excavated before the TBMs arrived. The first two TBMs arrived at the site from Paddington in October 2013 and January 2014, while the other two arrived from the east in May 2015, having started at the Limmo Peninsula at Canning Town: TBM Elizabeth arrived at Farringdon on May 9, 2015 and sister machine Victoria successfully broke into the Farringdon station site on May 23 at 05.30 in the morning, and in the process completed all the tunnelling work on the Crossrail project.
From February 2016 onwards the project became known by its future name – the Elizabeth Line. The TBMs were partly dismantled at Farringdon, with many parts, including the cutter heads recovered for re-use or recycling. The steel ‘cans’ forming the outer front part of the machines were all left underground in Farringdon, buried out of sight in specially built chambers next to the running tunnels in the stations.
The station site was excavated (both from the access shafts), and once they were in place from the new running tunnels the concrete rings produced by the TBM had to be partly removed to enable access to the platforms.
Continue reading your story on the app
Continue reading your story in the magazine
From Upminster To Upcycled: Vivarail's D-train
Ben Jones visits Long Marston to find out how redundant District Line trains are being rebuilt to provide cheaper and greener alternatives to brand new multiple units – and how Vivarail is looking to the future with new methods of propulsion.
Thameslink Franchise Not Delivering Value For Money
AN IN-DEPTH report by the National Audit Office (NAO) into the Thameslink, Southern and Great Northern (TSGN) rail franchise has revealed it has not delivered value for money as a result of high levels of passenger disruption.
Ro-railers Ahead Of Their Time Or Overtaken By Events?
A new type of vehicle for use on both road and rail was trialled in the early 1930s, but never caught on. Alan Dale considers whether early road-rail vehicles were too advanced for their time.
Count Down Getting Farringdon Ready For The Elizabeth Line
The first tunnel section of the Elizabeth Line – better known as Crossrail – is due to open next December between Paddington and Abbey Wood via Canary Wharf. Keith Fender has been given an exclusive tour of Farringdon, one of the major interchange points on the £16billion project
Tyseley Launches £3million Share Offer For New TOC
FROM the moment Tyseley unveiled its newly overhauled flagship locomotive No. 7029 Clun Castle at the end of October, fans of the Collett 4-6-0 began to ask when the famous BR(W) ‘Castle’will double-head with sister No. 5043 Earl of Mount Edgcumbe on the main line.
RAIB Report Outlines Croydon Tram Operator's Safety Failings
THE crash of tram No. 2551 on a bend at Sandilands, Croydon on November 9, 2016 was, in all probability, caused by the driver suffering a micro-sleep during a 49-second period when the tram was passing through three consecutive tunnels in the hours of darkness.
Bredgar's Little Gem
Gareth Evans visits the Bredgar & Wormshill Railway to discover the latest developments at the 2ft-gauge line in Kent, run by a group of friends, and open once a month to the public.
East Coast Bailout Row Overshadows Minister Grayling's 'New Vision For Rail'
SECRETARY of State for Transport Chris Grayling has unveiled his vision for the evolution of passenger rail franchising in the UK.
A Narrow Gauge Railway Under South London
Keith Fender reports on the construction of the Northern Line extension to Battersea, which has necessitated the construction of a narrow gauge railway under south London – albeit a temporary one.
Five To Bid For £2.75bn Hs2 Train Contract
Five To Bid For £2.75bn Hs2 Train Contract
TIGER WOODS CRASH: HOW IT HAPPENED!
Why he wasn’t charged! What an eyewitness saw!
‘HOME IMPROVEMENT' KID COPS TO 2 CHARGES OF DOMESTIC VIOLENCE
FORMER “Home Improvement” kid Zachery Ty Bryan has pleaded guilty to two felony counts of domestic violence.
BIDEN FACES STEEP CHALLENGES TO REACH RENEWABLE ENERGY GOALS
President Joe Biden wants to change the way the U.S. uses energy by expanding renewables, but he will need to navigate a host of challenges — including the coronavirus pandemic and restoring hundreds of thousands of lost jobs — to get it done.
‘GREY'S' ANARCHY!
Pompeo: No more Dr. McDreamy!
WILL PARAMOUNT+ BE A MOUNTAIN OR A MOLEHILL IN STREAMING?
Paramount+ debuts Thursday as the latest — and last — streaming option from a major media company, this time from ViacomCBS. It’s betting that consumers are willing to add yet another paid streaming service in an increasingly crowded field.
SPENDTHRIFT HABITS CHIP AWAY AT JOANNA!
Gaineses’ losses pile up as reno gurus leak money
COUNTRIES URGE DRUG COMPANIES TO SHARE VACCINE KNOW-HOW
In an industrial neighborhood on the outskirts of Bangladesh’s largest city lies a factory with gleaming new equipment imported from Germany, its immaculate hallways lined with hermetically sealed rooms. It is operating at just a quarter of its capacity.
HURRICANE KANYE DROWNING IN DESPAIR!
Fears that without Kim he’s spiraling down
GOOGLE ENDS SALE OF ADS USING INDIVIDUAL WEB TRACKING DATA
Google says it won’t develop new ways to follow individual users across the internet after it phases out existing ad-tracking technology from its Chrome browser, a change that could shake up the online advertising industry.
HARRY & MEGHAN'S $500M ROYAL GAMBLE
Throwing queen under bus to nab fancy future deals