Power Sector Strains Under Subsidies, Tariffs and Debt
Energy & Power
|EP_23_12 (Energy & Power Vol 22 Issue 12 December 1, 2025)
Prelude - Bangladesh's power sector is grappling with a wide range of challenges despite sustained government investments intended to build domestic and foreign confidence.
The problems span delayed bill payments, rising subsidies, tariff gaps, liquidated damage deductions, surplus generation capacity, contractual obligations, and more. Although infrastructure has expanded significantly and subsidies have surged, the country continues to face inefficiencies and mounting arrears that now threaten the sector's long-term sustainability.
Escalating Subsidies
The Bangladesh Power Development Board (BPDB) purchases electricity at high cost and sells it at lower regulated prices, requiring substantial government subsidies to cover the shortfall. Despite expanded generation capacity, Bangladesh remains heavily dependent on imported fuel, driving up production costs.
Over the last five fiscal years, the country has spent roughly Tk 1.474 trillion in subsidies. Between FY 2020-21 and FY 2023-24 alone, subsidies totaled Tk 854.11 billion, and the revised FY 2024-25 allocation represents an all-time high. From FY 2020-21 to FY 2024-25, electricity subsidies have increased by nearly 700%. (Table 1)
In the same five-year period, subsidies to the gas and LNG subsectors totaled Tk 680.54 billion, marking a 400% rise. (Table 2)
The core driver is Bangladesh's reliance on costly imported LNG, sold domestically at much lower rates. For example, Petrobangla's supply cost per cubic meter (NG + LNG) is Tk 29.39, while consumers pay only Tk 22.87, creating a significant revenue gap that subsidies must fill.
Unpaid gas bills further exacerbate fiscal stress. As of February 2025, industrial sectors owed more than Tk 210 billion to six major gas distribution companies. (Table 3)
Total arrears are expected to exceed Tk 230 billion once the March-April 2025 dues are counted. Despite this spending surge, the sector continues to suffer from deep inefficiencies, primarily due to rising costs associated with imported fuel and idle generation capacity.
Denne historien er fra EP_23_12 (Energy & Power Vol 22 Issue 12 December 1, 2025) -utgaven av Energy & Power.
Abonner på Magzter GOLD for å få tilgang til tusenvis av kuraterte premiumhistorier og over 9000 magasiner og aviser.
Allerede abonnent? Logg på
FLERE HISTORIER FRA Energy & Power
Energy & Power
Trump Admin Plans to Dismantle Leading Climate Center
The Trump administration intends to dismantle one of the world's leading climate research institutions over what it said recently were concerns of \"climate alarmism,\" despite opposition to the plan.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
Japan Govt Sued Over 'Unconstitutional' Climate Inaction
Hundreds of people across Japan sued the central government recently, seeking damages for “unconstitutional” inaction on climate change in the country’s first such litigation.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
Nearly 4.96m People Displaced by Natural Disasters in Bangladesh: IOM
Nearly 4.96 million are currently internally displaced persons (IDPS) caused by natural disasters in Bangladesh, according to the International Migration (IOM), Organization for which released its first comprehensive nationwide estimate.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
PDB Posts Record Losses
In the 2024-25 financial year, the Power Development Board (PDB) slid deeper into the red than ever before, its losses swelling to levels unseen since the country's modern power sector took shape.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
Nat'l Grid to Get Rooppur Nuclear Electricity Soon
Bangladesh could begin receiving electricity from its maiden nuclear power plant early next year, says Russia's ambassador, setting a milestone in one of the country's most infrastructure ambitious projects.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
Japan Prepares to Restart World's Biggest Nuclear Plant
The Japanese region of Niigata is expected to endorse a decision to restart the world's largest nuclear power plant recently, a watershed moment in the country's pivot back to nuclear since the 2011 Fukushima disaster.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
Bashundhara LP Gas Wins 'Best Brand Award' for 6th Year
Bashundhara LP Gas has clinched the prestigious \"Best Brand Award\" for the sixth consecutive year.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
Compensate Nations Affected by Climate Change
Two advisers of the interim government recently accused the Global North of failing to ensure climate justice and urged wealthy countries to provide proper compensation to climate change-affected nations like Bangladesh.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
Winter Slump Cuts Power Generation Sharply
Electricity generation across Bangladesh has fallen to nearly one-third of installed capacity as winter sets in and demand drops sharply.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Energy & Power
Excelerate Energy to Start LNG Supply from Early January
US-based Excelerate Energy is set to begin supplying liquefied natural gas (LNG) to Bangladesh from early January under a long-term contract, providing a fresh boost to the country's strained natural gas-supply system.
1 min
EP_23_14 (Energy & Power Vol 23 Issue 13 January 1, 2026)
Listen
Translate
Change font size