Why SC Ruling on Builder Liability Is a Shocker for Homebuyers
The New Indian Express Nagapattinam
|June 15, 2025
If your housing project is delayed by years, should you still be paying interest on the home loan? If the builder fails to deliver, should not that person bear the financial burden caused by the delay? And if the Supreme Court itself had to bring in the National Buildings Construction Corporation (NBCC) to complete stalled projects, does not that reflect a deeper structural failure, not just buyer impatience?
In a judgment that has rattled homebuyers across India, the Supreme Court has now said developers cannot be made to reimburse interest paid on home loans, even if they failed to hand over the property on time. Buyers are entitled only to a refund of the principal amount, along with contractual compensation, nothing more.
A bench of justices Sanjay Karol and Prasanna B Varale observed that there cannot be multiple heads for awarding damages or interest beyond what is contractually agreed upon. The court further held: "A perusal of the judgment and orders of the commissions does not reveal any exceptional or strong reasons for the interest on the loan taken by the respondents to be paid by GMADA (Greater Mohali Area Development Authority). That apart, whether the buyers of the flat do so by utilizing their savings, taking a loan for such purpose or securing the required finances by any other permissible means, is not a consideration that the developer of the project is required to keep in mind. For, so far as they are concerned, such a consideration is irrelevant."
The case was triggered by a complaint filed by Anupam Garg, who had booked a 2-BHK + Servant Room (Type II) flat under the 'Purab Premium Apartments' scheme launched by the GMADA in 2011. Garg paid ₹5.5 lakh as earnest money, which was 10% of the ₹55 lakh flat price.
Following a successful allotment through a draw of lots on March 19, 2012, GMADA issued a Letter of Intent (LOI) on May 21, 2012, outlining the flat's price, payment schedule, layout, ownership conditions, and possession date, which was May 2015. The LOI clearly stated that in case of delay, a refund with 8% interest would be given.
このストーリーは、The New Indian Express Nagapattinam の June 15, 2025 版からのものです。
Magzter GOLD を購読すると、厳選された何千ものプレミアム記事や、10,000 以上の雑誌や新聞にアクセスできます。
すでに購読者ですか? サインイン
The New Indian Express Nagapattinam からのその他のストーリー
The New Indian Express Nagapattinam
Dindigul youth hacked to death by dad-in-law in suspected caste killing
IN a suspected case of caste killing, a 25-year-old man was hacked to death by his father-inlaw near Nilakottai in Dindigul on Sunday evening.
1 min
October 14, 2025
The New Indian Express Nagapattinam
India, Canada to elevate ties through ministerial-level talks
INDIA and Canada on Monday agreed to upgrade bilateral relations through renewed ministerial-level talks, a revived energy dialogue, and a fresh push on trade and technology cooperation.
1 mins
October 14, 2025

The New Indian Express Nagapattinam
Mishra says India a leader in early warning collaboration on calamities
PARTICIPATING in the ‘G20 Disaster Risk Reduction Ministerial’, PK Mishra, the Principal Secretary to PM Narendra Modi, has showcased India’s leadership in financing and early warning collaboration in managing calamities.
1 min
October 14, 2025
The New Indian Express Nagapattinam
Gujarat RTI: Whistle-blowers silenced, data buried
TWENTY years after the Right to Information (RTI) Act came into force, Gujarat’s transparency story shows governance gaps.
1 mins
October 14, 2025
The New Indian Express Nagapattinam
Balveer Singh absent as trial opens in custodial torture case
THE much-awaited trial in the Ambasamudram custodial torture cases began on Monday, but the main accused, former ASP Balveer Singh, failed to appear before the court.
1 min
October 14, 2025

The New Indian Express Nagapattinam
Yogi okays restructuring of Invest UP, to set up expert cells and open offices
IN the first meeting of the Invest UP Governing Body, chaired by CM Yogi Adityanath on Monday, several key decisions were taken aimed at strengthening the state’s industrial investment ecosystem.
1 min
October 14, 2025
The New Indian Express Nagapattinam
SC: Have 2017 palliative care norms been met?
THE Supreme Court on Monday gave the Centre three weeks to update it on the implementation of 2017 palliative care guidelines issued by the Health Ministry.
1 min
October 14, 2025

The New Indian Express Nagapattinam
HCLTech reports flat profit at 4,235 cr in Q2, revenue increases 5% to 31,942 cr
IT major HCL Technologies on Monday reported a flat consolidated net profit of 4235 crore for Q2FY26 against same period in the last financial year.
1 min
October 14, 2025
The New Indian Express Nagapattinam
NAME MORE STANDS AFTER WOMEN CRICKET GREATS
UNDAY will go down asa red-letter day in women’s cricketing history for more reasons than one.
1 mins
October 14, 2025
The New Indian Express Nagapattinam
SIT probe plea into ‘vote theft’ in K’taka nixed
THE Supreme Court on Monday refused to entertain and pass an order on a PIL filed by lawyer Rohit Pandey seeking a Special Investigation Team (SIT) headed by a former judge to inquire into the allegations raised by Leader of Opposition Rahul Gandhi of large-scale electoral roll manipulation.
1 min
October 14, 2025
Listen
Translate
Change font size