No major work expected on Hamilton LRT until 2026
Toronto Star
|September 15, 2024
Pipe relocations and building demos continue next year
Metrolinx says work to move underground pipes out of the way of Hamilton’s long-delayed LRT will continue through 2025 — but the timeline for major construction on the “shovel-ready” project remains a mystery.
Metrolinx, the provincial transit agency in charge of the off-again, on-again light-rail transit project, says in a report presented to its board Thursday there has been “good progress” on preparatory works along the planned 14-kilometre rapid-transit line.
Those “enabling works” include utilities being moved out of the planned construction corridor of Main, King and Queenston, as well as ongoing property purchases and demolition — including 47 buildings knocked down as of this spring.
It remains unclear when the main LRT construction project will actually go to tender, however.
Diese Geschichte stammt aus der September 15, 2024-Ausgabe von Toronto Star.
Abonnieren Sie Magzter GOLD, um auf Tausende kuratierter Premium-Geschichten und über 9.000 Zeitschriften und Zeitungen zuzugreifen.
Sie sind bereits Abonnent? Anmelden
Listen
Translate
Change font size